PHOTOS - click image for slideshow»
Bridge Painting Process
Brian Sipe, project superintendant for S & K Painting calls the ODOT-approved painting system "the best corrosion protection system available for a bridge." The process steps are:
- Build containment system
- Sandblast existing paint to bare metal with LEADX product that renders old paint non-hazardous
- Collect and return sand to manufacturer for recycling
- Inspection (additional inspections occur between each coat)
- Apply full coat of zinc primer
- Apply stripe coat (around irregular edges and rivets) of Wasser paint
- Apply stripe coat of Ferrox B paint
- Apply full coat Ferrox B paint
- Apply final full coat of Ferrox A green paint
- Remove containment system
Bridge painting progresses
as weather allows
A significant capital maintenance project on the Hood River
Interstate Bridge has been underway since early August,
and due to early reports that the bridge is in relatively sound
condition, additional sections have been added to the first phase
of the Lower Chord Rehabilitation Project.
The scope of the project originally focused on prepping and
painting the connections (gusset plates) on the lower chords,
which run the full length of the bridge closest to the water and are
the most "fracture critical" members, and out at least six inches
on all the vertical and diagonal connectors. The contractor was
also directed to do spot painting work where severe pack rust was
found in other locations along the lower chords. See photos here
After the first month of work, and positive reports about the
condition of the connections once stripped of paint, the Port
Commission added the full length of the lower chord north of the lift
span to the project. These represent the next most fracture critical
components, and would have been rehabilitated in a future phase.
Although the bridge paint is showing wear, and there are bare
spots and surface rust on some sections, the steel inspected thus far
has not demonstrated extreme corrosion or pitting. This means the
additional lower chord work can be sandblasted to a lower degree
than the connections, called a "brush off blast," then recoated.
Adding the entire lower chords on the north half of the bridge to
the project is more economical in the long run, since equipment
and crew are mobilized, and scaffolding and containment in place.
However, the Port Commission was uncertain its cash flow would
allow it until it received reports that the project was proceeding
without major pack-rust or corrosion repair work.
The Port estimated $250,000 per span for fracture critical
member spot painting, which totals $4.75 million for all 19 spans.
The Port has budgeted approximately $1 million per year for the
next fi ve years. The contractor will complete as many northern
spans as possible in 2011 before heavy rain patterns set in. Ideally,
any remaining northern spans and all the southern spans will be
completed in 2012, beginning in spring as early as weather permits.
A second phase to the bridge painting project
will now likely include painting the upper chord
connections, cross bracing, and components just below
the deck. The Port Commission will decide when that
phase will begin within the next few years.
S & K Painting, a 38-year-old Oregon company,
is the contractor for the Lower Chord Rehabilitation
Project. HNTB provides construction management
and engineering, and Bear Inspecting and Consulting
provides inspection services. As the painting project
progresses, needed repair work may be noted and
possibly performed.
Brian Sipe, project superintendent for S & K
Painting, has worked in the industry for 25 years,
but never on a mile-long bridge such as the Hood
River Interstate Bridge. After two months of work,
S & K is partway through the fourth span.
"We just started, but by the time this Lower Chord
fi rst phase is over, we'll really know what kind of shape
the bridge is in. With a good painting system like this,
our work will last 30 years or more, but the entire bridge
will need to be done eventually," Sipe relayed.
Single lane closures will continue throughout the
project. The Port urges bridge patrons to allow for delays
anywhere from fi ve to 15 minutes, between 6:00 a.m.
and 4:00 p.m. Monday through Friday. By and large
delays have been limited to fi ve minutes. Bridge users
can sign up for electronic notifi cations of bridge traffic
delays or closures at: www.portofhoodriver.com